UBY helps ensure a trouble-free experience for residents during the Pawtucket Tunnel project
The Project
Two miles of tunnel needed to be created in a densely populated area of New England near a state capital, as part of the Narragansett Bay Commission’s CSO (Combined Sewer Overflow) programme. The public body commissioning the work wanted strong assurance that life would not be disrupted for local residents. UBY’s monitoring solutions allowed construction managers to oversee works confidently, and resolve complaints fast.
Summary
Client : Narragansett Bay Commission
Contractor: CB3A consortium (CBNA, Barletta Heavy Division and AECOM)
Project type: Public works; tunnels
CB3A contract: $479.4 million
Project duration: 48 months
Tunnelling start: December 2022
UBY solutions used: UBY Environment
Site Overview
Narragansett Bay is a large natural harbour in Rhode Island, and New England’s largest estuary. The Narragansett Bay Commission, a non-profit public corporation, was created in 1980 and tasked with improving the water quality of the bay and its tributaries.
The “big dig” is the nickname for the Narragansett Bay Commission’s $1.5 billion CSO programme. Creation of the new Pawtucket Tunnel is the third and final phase of the big dig. A tunnel boring machine is being used to create a 2.2-mile tunnel alongside the Seekonk River. This tunnel will combine wastewater and potential flood water, and carry it safely to the Bucklin Point Wastewater Treatment Facility.
CB3A consortium turned to UBY to supply the sound and vibration monitoring solution required throughout the 4-year tunnel construction programme, as well as to provide software to manage communication with residents.
Image: Narragansett Bay Commission (NBC)
The Challenge
Tunnel boring operations are inherently noisy, and the bay is the site of the state’s capital, Providence, among other communities, so careful monitoring of both noise and vibration is needed throughout the project.
Image: Bouygues Group
The potentially affected area includes schools and hospitals as well as housing, and the consortium needed a solution that would enable managers to monitor noise and vibration without any continuous need to check in to a software platform, and which would help them resolve any threshold breeches or resident complaints as quickly and efficiently as possible.
UBY Solution
A network of smart, acoustic and vibration sensors were deployed across five sites identified as noise sensitive. Data was collected and linked to our online platform – in real time, allowing managers to check the current noise and vibration at any time. They would only need to do this following an issue, since user-defined thresholds were set up to generate automatic alerts.
If such an issue did arise, the system went well beyond a traditional decibel reading. UBY’s own AI algorithms, embedded in the smart sensors, are capable of identifying the source of the sound, differentiating between jackhammers, traffic and other numerous noise categories, also allowing users to see visually the location of the source.
After receiving one particular noise complaint, the site supervisor was able to access the dashboard and immediately identify the cause (the ventilation system, with noise the result of human error in the launch shaft area) and act without any delay or further, potentially time-consuming investigation.
Benefits
When asked about the system, project managers highlighted the value of the automatically generated and customised weekly reports, which traditionally they would have needed to create manually.
Overall, UBY’s solutions resulted in a better experience for residents, accomplished with much less investment of managerial time for the contractor than would be required with traditional solutions.
Related case studies:
Fécamp Offshore Wind Farm: Structural health monitoring for EDF
UBY state-of-the-art sensors provide long term condition monitoring in challenging marine environment
Lille-Europe: Monitoring air quality and worker geolocation for Colas Rail
Ensuring worker safety during extensive night-time renovation works at this high-speed train station in northern France
Bouygues Travaux Publics: Lock of Méricourt
Monitoring and control of the impacts of the construction site on water quality